KEY PROJECTS EXECUTED :

  • Erection, Testing & Commissioning 400/132 kV Switchyard with BHEL for NTPC at VSTPP, Vindhyanagar (MP), Stage-II consisting of 10 Bays.
  • Erection, Testing & Commissioning of 400/132KV Switchyard with BHEL for NTPC at VSTPP-Vindhyanagar, (MP), Stage –III. Consisting of 15 Bays.
  • Erection, Testing & Commissioning of 400/132 kV Switchyard with BHEL for NTPC at RhSTPP, Rihand Nagar (UP), Stage-II consisting of 13 Bays and One 200MVA, 400/132KV Transformer.
  • Civil Works, Erection, Testing & Commissioning of 220 kV Sub-stations Gurgaon and Krukshetra for HVPNL Haryana consisting of 41 Bays & 6 Nos. of 100 MVA Power Transformers, Control Room Buildings, Boundary Wall, Roads & Foundations etc.
  • Supply, Civil works, Erection, Testing & Commissioning of Arya Nagar, Jakhal & Bhutan (Hissar) and Beri & Mundlana (Rohtak) 132 KV Sub-stations for HVPNL Haryana consisting of all Electrical System for 52 Bays & 15 Nos 25 & 16 MVA Power Transformers, Control Room Buildings, Boundary wall, Roads & Foundation etc.
  • Providing additional Power Transformer at 132KV Substation at 8 locations on turnkey basis for HVPNL Haryana.
  • Erection, Testing & Commissioning of 2 Nos. 50 MVAR Shunt Reactors along with 4 Bays of 400 KV Sub-stations with BHEL for Power Grid Corporation of India Ltd. at Rourekela & Jeypore (Orissa)
  • Erection, Testing & Commissioning of 11KV Sub-station, External Electrification & Communication System. The work was consisting of 500 Poles, 80 Kms LT Cables and 37 Kms HT cables etc in Township of IOC Panipat Refinery, Haryana.
  • Erection, Testing & Commissioning of Electrical Equipments and Lighting System for Main Plant Area comprising of different units as FCC, H2U, HCU, BBU, MEROX. The work involved laying of 600 Km cabling for IOCL Panipat Refinery Project, Haryana.
  • Design, Supply, Erection, Testing & commissioning of 33/11 kV substations along with associated civil works for M/s National Hydro Power Corporation Limited at Dharchula, Pithorgarh in Uttarakhand.
  • Laying, Testing & Commissioning of Cables, 66/33/11KV grade, total length of 175 Km with Reliance Energy Ltd. for Delhi Power Distribution System Delhi.
  • Design, Survey, Supply, Erection & Testing of High Voltage Distribution System with NDPL consisting of 300 Transformers of different sizes for Delhi Power Distribution System Delhi.
  • Erection, Testing & Commissioning of 33/11KV Sub stations with Reliance Energy Ltd for REC, Aligarh, (UP). This includes 2 Nos. Sub-stations along with Control Room Building, Roads, Boundary Wall, Foundations and 120 Kms of incoming & outgoing overheads lines.
  • Erection, Testing & Commissioning of 11KV O/H lines for Reliance Energy Ltd. for Power Grid Corporation of India Ltd. in Raibareily (U.P.). This includes 643 Transformers and 15000 BPL Connections.
  • Erection, Testing & Commissioning of 11KV O/H lines for Reliance Energy Ltd. for Power Grid Corporation of India Ltd. in Raibareily (U.P.). This includes 643 Transformers and 15000 BPL Connections – Phase II.
  • Supply, Civil Works, Erection, Testing & Commissioning of 132 KV Substation for HVPNL Haryana which includes 29 Bays & 12 Nos. 25/16 MVA Power Transformers, Foundations, Control Room Buildings, Boundary wall, Roads etc complete in all respects.
  • Erection, Testing & Commissioning of 220/33 KV Switchyard with BHEL for Neyveli Lignite Corporation Limited at Barsingsar, Rajasthan. This includes 10 Bays and 2 Nos. 150MVA Generator Transformers, 2 Nos. 100MVA, 2 Nos. 20MVA and 2 Nos. 20MVA and 2 Nos. 16MVA Power Transformers.
  • Erection, Testing & Commissioning of 220/33 KV Switchyard with BHEL for Delhi Transco at Masjid Moth, Delhi. This includes 8 Bays and 2 Nos. 100MVA Power Transformers.
  • • Civil Construction of various foundations for Transformers, Fire Walls, Cable Trenches and other offsite work of 2X660 MW gas based Thermal Power Project for Pragati Power Ltd. At Bawana in Delhi.